Project Overview

The gas turbine Automation is driven by ABB Advant Control system for the sequential operation and protection of the gas turbine. When a critical gas turbine project stalled due to hardware failure, Unitritech delivered the technical precision needed to get it back on track. Specialising in ABB Advant automation, our engineers replaced damaged PM651 controllers and optimized system logic to ensure robust turbine protection and operation sequencing. We don't just fix hardware; we commission reliability.